Conformity assessment according to national requirements
"STROYCONTROL 2003" Ltd. is authorized by the Ministry of Regional Development and Public Works (MRDPW) to assess the conformity of construction products with national requirements, holding Authorization No. ROSSP 06 since September 15, 2016.
Concrete – according to Order No. RD-02-14-1329/03.12.2015 of the Minister of Regional Development and Public Works, Annex No. 2, item 1
External Thermal Insulation Composite Systems (ETICS) – according to Order No. RD-02-14-1329/03.12.2015 of the Minister of Regional Development and Public Works, Annex No. 2, items 13 and 14
Unbound mixtures – according to Order No. RD-02-14-1329/03.12.2015 of the Minister of Regional Development and Public Works, Annex No. 2, item 9
Hydraulically bound mixtures – according to Order No. RD-02-14-1329/03.12.2015 of the Minister of Regional Development and Public Works, amended and supplemented by Order No. RD-02-14-590/05.07.2017, Annex No. 3, items 10.1, 10.2, 10.3, 10.4, 10.5, 10.6
Steel products for the reinforcement of reinforced concrete structures – according to Order No. RD-02-14-1329/03.12.2015 of the Minister of Regional Development and Public Works, amended and supplemented by Order No. RD-02-14-590/05.07.2017, Annex No. 3, items 1.1, 1.3, 1.4, 1.5
The specific national requirements and procedures are publicly available on the website of the Product Contact Point of the MRDPW: cpcp.mrrb.government.bg
Developed by the Association of Construction Product Conformity Assessment Bodies (ALOSSP) and approved by the MRDPW, the assessment procedure consists of the following steps:
Acceptance and registration of the application, review of documents, and contract signing.
Option 2.1 Full Verification: Sampling and testing/calculation.
Option 2.2 Documentary Assessment: Recognition of test results from another accredited laboratory.
Option 3.1 Full Inspection: Initial on-site inspection (audit) at the production facility.
Option 3.2 Documentary Assessment: Review of documents based on a valid Quality Management System certificate.
Preparation of the report and decision on certification.
Option 5.1 Full Inspection: Periodic on-site inspection of the factory production control.
Option 5.2 Documentary Assessment: Review of documents and records based on a valid management system certificate.
This is carried out only for products where specified in the applicable product standard.
Preparation of a report with a recommendation on the certificate's validity.